Richard Simpson Construction Progress – May

Friday, 01 June 2018 00:00

Progress continues at Richard Simpson Park as the new Lake House structure really starts to take shape. The concrete building foundation is complete along with the installation of the vertical walls. The waterline cut across Arkansas Lane is also complete. The project as a whole is approximately 35% complete.

Over the next 30 days:

    • The Building stone facade will continue to be constructed
    • Interior building work will be ongoing for the next 7 months
    • Parking lot demolition and new concrete drive to be constructed
    • New concrete drop off at building entrance off Arkansas Lane to be constructed
    • Trash dumpster screen wall to be constructed

RSLP-May1RSLP-May2

Phase one of park redevelopment improvements started late October 2017. The $3.5 million project, scheduled to be complete by December 2018, aligns with the Arlington City Council priority to Champion Great Neighborhoods. Construction is funded through the 2008 Bond Referendum and Arlington Tomorrow Foundation.

For the master plan, click here. For a project overview, click here.

Last modified on Friday, 01 June 2018 14:06
Subscribe to Naturally Fun!

Sign up for the Naturally Fun newsletter and receive weekly updates on program offerings, classes, and special events.

Gold Medal Finalist

gold-medal-finalist-2016

The City of Arlington Parks and Recreation Department was recently named a Gold Medal Finalist for excellence in Park and Recreation Management by the National Recreation and Park Association for 2017.

Learn More

Naturally Fun News

News and updates from Arlington Parks and Recreation.

Read the Blog

Find a Park

Explore Arlington's 90+ parks with the Park Finder!

Find a Park